Asbestos removal
Floor tile and mastic, carpet adhesive, thermal system insulation, transite materials, window putty, and roofing mastics.
Pomona, California
A tightly coordinated asbestos and lead project spanning classrooms, vocational buildings, restrooms, and support areas—completed against a strict 40-business-day schedule.



01 / Project overview
JJ&S Environmental Services completed a large-scale asbestos and lead abatement project across several buildings at a Pomona Unified School District facility.
Hazardous materials were present in flooring systems, structural beams, pipe insulation, wall tile, windows, roof components, and other building materials. The work required careful sequencing between interior and exterior areas, consistent containment procedures, and disciplined schedule control.
02 / The challenge
Separate building conditions had to be managed as one project. Crews moved through machine and auto shops, classroom and locker buildings, restrooms, mechanical spaces, exterior windows, and roof areas while maintaining the appropriate controls for each material and location.
03 / JJ&S response
The team translated a 32-item technical scope into coordinated work zones, material-specific abatement, cleanup, disposal, and clearance preparation.
Floor tile and mastic, carpet adhesive, thermal system insulation, transite materials, window putty, and roofing mastics.
Loose and flaking lead-based paint was scraped and structural steel surfaces were encapsulated across three buildings.
Interior negative-air containments and exterior containment systems supported work across multiple areas.
Targeted P5 report cleanup, biohazard cleaning, wet wiping, HEPA vacuuming, and hazardous-waste disposal.
04 / Scope in detail
The itemized scope addressed more than 37,000 square feet of asbestos-containing materials and lead-painted surfaces, plus specialized window, roof, and biohazard work.
05 / The outcome
JJ&S executed the multi-building scope within the project’s demanding schedule and prepared the affected areas for clearance and subsequent construction activity.
From regulatory notification and negative-air containment through hazardous-waste hauling and clearance coordination, each phase was planned to protect people, property, and the project timeline.