Project takeover
JJ&S assumed the active abatement scope and organized the remaining work for focused execution.
Arcata, California
JJ&S mobilized 20+ certified technicians within two days and completed more than 20,000 square feet of asbestos removal in two weeks. Finishing ahead of a three-week deadline.



01 / Project overview
JJ&S stepped into an active asbestos abatement project at Humboldt University and assumed responsibility for completing the remaining work.
With only two days’ notice, the team mobilized more than 20 certified technicians to Arcata and established a seven-day work schedule. The objective was clear: recover the schedule and finish before the general contractor’s three-week deadline.
02 / The challenge
The abatement project was already underway when JJ&S was called in. The team had to understand the remaining work, mobilize a large certified crew, and establish a productive field rhythm without a long transition period.
03 / JJ&S response
More than 20 certified technicians were deployed within two days and worked seven days a week to complete the active-project takeover on an accelerated schedule.
JJ&S assumed the active abatement scope and organized the remaining work for focused execution.
More than 20 certified technicians were deployed to the Humboldt project within two days.
Crews worked seven days a week to maintain momentum and compress the completion timeline.
The 20,000+ square-foot removal was completed in two weeks (one week ahead of deadline).
04 / Delivery at scale
The accelerated plan paired fast staffing with continuous field execution, allowing JJ&S to complete the asbestos removal ahead of the general contractor’s three-week deadline.
05 / The outcome
JJ&S completed more than 20,000 square feet of asbestos removal in two weeks, one week before the general contractor’s deadline.
The result demonstrates the team’s ability to take over an active job, mobilize a large certified workforce quickly, and restore project momentum under schedule pressure.
Project gallery









Swipe or scroll horizontally to view all six additional photos.
Need help recovering an active asbestos project?